Eighty One Wellesley

Sold Out

  • Location

    Toronto, ON

  • Units

    179

  • Architect

    Core Architects

  • Building Type

    Concrete

  • Completion Date

    2022

Project Timeline

MAY 2022
April 2022
March 2022
February 2022
January 2022
November 2021
October 2021
September 2021
August 2021
August 2021
July 2021
June 2021
May 2021
April 2021
March 2021
February 2021
January 2021
MAY 2022

APRIL 2022 UPDATE

Masonry on north elevation continues. Interior work continues.

April 2022

March 2022 Major Milestones

Tower Crane was dismantled and removed from the building. Pre-cast panels have all been installed.

March 2022

February 2022 Update

Balcony railings frame and glass continues being installed. Plumbing and electrical wiring continues throughout the building.

February 2022

January 2022 Update

Precast continues to be placed. Passenger elevators are being installed. Drywalling of suites continues.

January 2022

December 2021 Update

Concrete structure is now substantially complete. Views from the top!

November 2021

November 2021 Update

The final floor slab has now been poured with only one set of walls and the roof to complete. Work continues on both the exterior and interior of the building.

October 2021

October 2021 Update

We are approaching the top of the building with the 28th floor walls being worked on. At the same time, drywall installation has started on the lower floors.

September 2021

September 2021 Update

Brick work completed on east elevation. During September our forming contractor experienced a COVID outbreak amongst their crew. As a result, they were unable to work for the better part of two weeks. While no other trades were impacted directly, work was slowed substantially, especially while the crane operator was not on site.

August 2021

August 2021 Update

Brick work continues on east elevation. Windows and exterior doors continue to be installed as do interior steel studs.

August 2021

July 2021 Update

Brick work beginning on east elevation. Windows and precast continue being installed.

July 2021

June 2021 Update

Brick work complete on west elevation. Both car elevators now complete.

June 2021

May 2021 Update

Brick work is now underway. Precast panels continue to be installed.

May 2021

April 2021 Update

Windows are being installed. The scaffold system installed so that the masonry can begin.

April 2021

March 2021 Update

The Tower Crane has been raised again. Work continues above ground, below ground, and on the interior and exterior walls.

March 2021

February 2021 Update

In spite of a few days lost to -20 degree temperatures and snow, construction continues. Precast concrete is being hung, interior block walls are being placed, and installation of steel studs has commenced as well. The first car elevator is operational.

February 2021

January 2021 Update

Construction continues while all health and safety protocols, including those for COVID, continue to be followed. Installation of precast panels continues; west side of ground floor nears completion.

January 2021

December 2020 Update

Construction continues while all health and safety protocols, including those for COVID, continue to be followed.

Next Arrow

AT HOME 

IN THE

VILLAGE

Rising 28 storeys above the Church-Wellesley Village in downtown Toronto, 81 Wellesley is a sophisticated addition to a vibrant neighbourhood. Outdoor and retail spaces were designed to encourage interaction, inviting people to slow down and spend time with neighbors and friends. We carried the mid-century modern aesthetic of the exterior architecture into the interiors, which are stylish yet unpretentious.