​​Esquimalt Townhouses condos and lofts, Oakwoods by Aragon Properties, esquimalt community
​​Esquimalt Townhouses condos and lofts, Oakwoods by Aragon Properties, esquimalt community

Oakwoods

Coming Soon

  • Location

    Esquimalt, BC

  • Units

    180 Condos and Townhomes

  • Architect

    Merrick Architecture, Lovick Scott Architects

  • Building Type

    Residential Wood Frame

  • Completion Date

    Est. 2024

  • Property Type

    Residential

Project Timeline

August 2023
April 2023
September 2022
June 2022
May 2022
April 21, 2022
April 2022
February 2022
January 2022
November 22, 2021
November 17, 2021
August 2021
October 2016
July 2016
June 2016
May 2016
October 2015
August 2023

Construction Updates

Building 1: All windows are installed, and the cladding assembly is more than 50% complete. Interior works are focused on progressing the rough-in and preparing for drywall. Building 2: Roof framing is in progress with completion expected in August, Roofing installation has commenced at the West end of the building. Building 3: Framing is complete to level 4. Pre-fabrication of the remainder of the walls is almost complete.

April 2023

Construction Updates

Building 1: Roof framing is at 80% and framing is 97% complete overall. Roofing and window installation has started in areas where roof framing is complete. Plumbing rough-ins will be complete to the roof for the whole building by mid-April. HVAC, sprinkler and electrical rough-ins are following in behind. Building 2: Framing is 60% complete overall. Level 4 walls are 80% complete. Building 3: Pre-fabrication of the walls will begin off site in April, with site installation to begin in June.

September 2022

Construction Updates

The 2-level parkade is on track for substantial completion by the end of September. Building 3 East is in a near finished state. The remaining buildings will be completed in a phased manner. The first phase will be partial occupancy of the parkade plus Building 1, followed by Building 2, Building 3 West, and the townhouses. Framing is well underway for Building 1, with framing progressing between levels 2 and 4. The roof should be installed by the end of the year. Occupancy for the first phase (partial parkade and Building 1) is targeted for year end, 2023.

June 2022

Construction updates

As we enter summer, construction efforts are now focused on two fronts: framing Building 1 (71 condo units) and completing the parkade structure. Framing of Building 1 is well underway with the first section of Level 1 completed. Construction of the parkade is now well over the half-way mark and we are targeting a September finish for the Level 1 plaza slab. On the design side, we had a digital construction company CADMakers build a 3D model of the project for the purpose of coordinating disciplines and improving the drawings. The 3D model is complete and consultants are now finalizing their u… Read More

As we enter summer, construction efforts are now focused on two fronts: framing Building 1 (71 condo units) and completing the parkade structure. Framing of Building 1 is well underway with the first section of Level 1 completed. Construction of the parkade is now well over the half-way mark and we are targeting a September finish for the Level 1 plaza slab. On the design side, we had a digital construction company CADMakers build a 3D model of the project for the purpose of coordinating disciplines and improving the drawings. The 3D model is complete and consultants are now finalizing their updates to the drawings. Read Less

May 2022

Construction update

Construction of the two-level parkade is now past the 50% complete mark and we nearing completion of slab on grade at the last section. The structure should be completed this summer. Framing of Building 1 (71 units) is starting May 30. The framing contractor has been building wall panels off site for the past two months and walls are ready for more than half the building already. The crane(s) will be busy!

oakwood-update-may-2022
April 21, 2022

News

On Thursday April 21st we welcomed Mayor Desjardins and Councillors Morrison and Hundleby for a very special construction tour of Rosemeade and Oakwoods, led by Arie! The Council was blown away by the amount of work we are doing, and are very appreciative of our attention to detail when it comes to the Rosemeade renovation. Overall, it was a very successful tour.

oakwood-update-apr-2022-3
oakwood-update-apr-2022-4
April 2022

Construction Update

Construction of the two level parkade is progressing well. At the first section, concrete is now being poured at the Level 1 plaza slab (top of parkade), while ground preparation and foundation work is being completed for the last sections. The framing contractor has commenced building pre-fabricated walls off-site, and the on-site build of our first wood frame building, Building 1 (71 condo units) is set to begin in May. At the historic Rosemeade hotel building, which is undergoing a major renovation, construction activity is ramping up. The current focus is on structural renovations and … Read More

Construction of the two level parkade is progressing well. At the first section, concrete is now being poured at the Level 1 plaza slab (top of parkade), while ground preparation and foundation work is being completed for the last sections. The framing contractor has commenced building pre-fabricated walls off-site, and the on-site build of our first wood frame building, Building 1 (71 condo units) is set to begin in May. At the historic Rosemeade hotel building, which is undergoing a major renovation, construction activity is ramping up. The current focus is on structural renovations and mechanical upgrades while window and façade restoration is set to begin this summer. Read Less

oakwood-update-apr-2022-2
oakwood-update-apr-2022-1
February 2022

Construction Update

Despite difficult weather, great progress was made on the parkade in January. Our first sections of slab on grade were poured and we just completed our first section of suspended slab. By the end of February we will have the first section of L1 plaza slab erected. We are on track to have the concrete build of the parkade finished this Spring. Framing of our first building, Building 1 (71 condo units), is scheduled to commence in April.

oakwood-update-feb-2022
January 2022

Construction Update

Our crane is up! Shotcrete is now underway + the parkade is taking form. Excavation of the balance parkade continues with line drilling + blasting progressing southward on the site. Excavation will complete early in the year with the concrete portion of the parkade complete in the spring. We look forward to framing commencing shortly thereafter.

oakwood-update-jan-2022-1
November 22, 2021

Construction Update

The parkade excavation is currently underway. Site servicing is also commencing.

November 17, 2021

Development Update

Approved for Condo Building.

August 2021

Construction Update

Excavation of the parkade is proceeding swiftly with line drilling and blasting nearly complete on the first zone of the parkade. We now have a formwork trade on board + are strategizing to keep things rolling with footings commencing in September + targeting a parkade completion in April.

October 2016

Tree Relocation and Transplanting

Several of the sites trees are transported to the new tree garden to preserve as much tree life as possible.

July 2016

DEVELOPMENT UPDATE - APPLICATION FOR DEVELOPMENT PERMIT

Aragon applies for a Development Permit from the Town of Esquimalt.

June 2016

DEVELOPMENT UPDATE - ARBOURIST HIRED

Local Arbourist is hired to develop a Tree Protection Plan.

May 2016

DEVELOPMENT UPDATE - PRELIMINARY DESIGN COMPLETED

Merrik Architects complete a Preliminary design for the site.

October 2015

DEVELOPMENT UPDATE - PARKING STUDY COMPLETED

Preliminary Parking Study Completed to asses demand of parking needed for the site to eliminate parking conflicts with nearby residents.

Next Arrow
​​Esquimalt Townhouses condos and lofts, Oakwoods by Aragon Properties, esquimalt community

MADE 

BY

HISTORY

​​Esquimalt Townhouses condos and lofts, Oakwoods by Aragon Properties, esquimalt community

Coming Soon- Oakwoods is a new collection of heritage-inspired residences and townhomes set in a historic location just minutes from the water. Surrounded by manicured, European-style gardens, this is an ethereal destination where privacy meets discovery. Register today.

Register Today