755 Cordova Bay Road

In Development

  • Location

    Cordova Bay, BC

  • Units

    Not Yet Available

  • Architect

    Not Yet Available

  • Building Type

    Not Yet Available

  • Completion Date

    Not Yet Available

  • Property Type

    Residential

Project Timeline

October 2017
October 2017
June 2017
November 2016
August 2016
April 2016
March 2016
July 2015
June 2015
May 2015
January 2015
January 2000
January 1966
October 2017

Planning Update

The development of the Trio Gravel Pit at Cordova Bay is still in the planning stage. Aragon has been working to bring a new design forward which will address the feed back we received during the last rezoning application, as well as the feedback we have heard from the community since then. Updates will be posted to this website to keep the community informed. If you have feedback or would like further inform

October 2017

Aragon Makes Application for deposit of fill - 1

Aragon makes an application to deposit fill at the North end of the Cordova Bay site. As part of the Esquimalt Town Square (ETS) Project, in which Aragon is building a mixed use project complete with a Library which will be completed for the township. The fill excavated from one level of underground parking at the ETS project is proposed to be transported to Cordova Bay and placed at the North End of the old Trio Gravel Pit. The fill is proposed to be moved to a location which where it will sit below the original grade of the site, prior to the gravel mining. This fill is not intended to be… Read More

Aragon makes an application to deposit fill at the North end of the Cordova Bay site. As part of the Esquimalt Town Square (ETS) Project, in which Aragon is building a mixed use project complete with a Library which will be completed for the township. The fill excavated from one level of underground parking at the ETS project is proposed to be transported to Cordova Bay and placed at the North End of the old Trio Gravel Pit. The fill is proposed to be moved to a location which where it will sit below the original grade of the site, prior to the gravel mining. This fill is not intended to be connected to any development proposal at Cordova Bay. Read Less

June 2017

Meeting with Cordova Bay Community Association

Aragon held a meeting between members of the Cordova Bay Community Association to discuss the relocation of the Cordova Bay Badminton Club into the proposed development. The Geotechincal Engineers presented new data from recent soil testing which outlined the locations where it is difficult to build density due to poor soil conditions. Preliminary ideas about a location for the badminton club were proposed and there was an informed discussion regarding where buildings might be placed in the future development. During the meeting it was discussed that in order to provide space for the badmi… Read More

Aragon held a meeting between members of the Cordova Bay Community Association to discuss the relocation of the Cordova Bay Badminton Club into the proposed development. The Geotechincal Engineers presented new data from recent soil testing which outlined the locations where it is difficult to build density due to poor soil conditions. Preliminary ideas about a location for the badminton club were proposed and there was an informed discussion regarding where buildings might be placed in the future development. During the meeting it was discussed that in order to provide space for the badminton club the units displaced would likely be relocated to a taller building. Read Less

November 2016

3rd Community Design Consultation

Community meeting held and further comments taken to revise concept plan.

August 2016

RESUBMIT REVISED MASTER SITE PLAN

“FOURTH CONCEPT PLAN” The master site plan design revisions include (but is not limited to): Density reduced from 330 to 309 homes Reduction of 6 storey building to 4 storey at the Cordova Bay Road entrance Elimination of the Cordova Bay townhouses and replacement with two single family lots Revised and up-dated Traffic Study to address the neighbourhood concerns

April 2016

REVISION REQUEST FROM DISTRICT OF SAANICH

District of Saanich has requested elimination of the seven residential units fronting onto Cordova Bay Road in the West side of the site, along with a reduction in the number of units in the North side of the site to bring the density closer to +300 homes.

March 2016

REVISED MASTER SITE PLAN

“THIRD CONCEPT PLAN” Aragon presents revised master site plan to District of Saanich/Planning Department and CBA. The revised site plan has been reduced from a unit count of 385 to 330 homes

July 2015

PRELIMINARY REZONING APPLICATION

THE “SECOND CONCEPT PLAN” Based on comments received from the neighbourhood and other public input, the First Concept Plan was revised to address these concerns and a revised plan was prepared. Aragon submits the Preliminary Rezoning Application to the District of Saanich. The revised zoning application addressed public concerns and revised density to 385 homes.

June 2015

2ND COMMUNITY DESIGN CONSULTATION

Aragon presented the First Concept Plan to the Neighbourhood and the public. Further ideas incorporated into design process for future plans.

May 2015

1ST COMMUNITY DESIGN CONSULTATION

Solicited community member’s ideas. Over 100 people were in attendance leaving their comments on the development design. The following five principles were taken from the February 21 meeting and applied to the design of the master plan community: A diversity of housing form is essential for community building and affordability Connectivity and open space are central requirements Moderate density and height are supportable if we respect views and good planning The plan must add to neighbourhood amenity and fit the community Commercial uses should build on the success of Mattick’s Farm

January 2015

PRELIMINARY REZONING REVIEW BY DISTRICT OF SAANICH

District of Saanich reviews submission and presents further concerns and requirements to Aragon.

January 2000

TRIO LANDS MINE STOPS PRODUCTION

Mining and production stops at the Trio Lands Gravel Pit.

January 1966

TRIO LANDS GRAVEL MINE OPENS

The original gravel pit mining begins

Next Arrow
755 Cordova Bay Road by Aragon Properties, cordova bay community

COMING 

SOON

755 Cordova Bay Road by Aragon Properties, cordova bay community

Aragon is excited to bring a master-planned community to the beautiful Cordova Bay neighborhood in Saanich, BC. More details will be released as they become available. To receive updates, please register below.