Toronto Studio, 1 - 3 bedroom condos, Eighty One Wellsey by Aragon Properties, highrise, downtown toronto, the village Toronto

Eighty One Wellesley

Available for Lease

  • Location

    Toronto, ON

  • Units

    179 condos and 920 sq.ft retail space

  • Architect

    Core Architects

  • Building Type

    Concrete

  • Completion Date

    2022

  • Property Type

    Residential

Project Timeline

September 2023
May 2023
April 2023
March 2023
February 2023
January 2023
December 2022
November 2022
October 2022
September 2022
July 2022
June 2022
May 2022
April 2022
March 2022
February 2022
January 2022
November 2021
October 2021
September 2021
August 2021
August 2021
July 2021
June 2021
May 2021
April 2021
March 2021
February 2021
January 2021
November 2020
October 2020
September 2020
August 2020
July 2020
June 2020
May 2020

September 2023

AUGUST 2023

"Heavy Handed L.O.V.E." Artwork, based on the word LOVE in sign language, was installed. Condominium was registered on August 31st. Final closings to occur in September.

May 2023

APRIL 2023

Occupancies continue to be received from the City and finishing work continues throughout the building.

April 2023

MARCH 2023

The first round of occupancies has taken place. Work continues on both the interior and exterior of the building.

March 2023

FEBRUARY 2023

Work continues on both the interior and exterior of the building. Exterior hoists have been removed.

February 2023

JANUARY 2023

Work continues on both the interior and exterior of the building. Exterior hoists are being prepared for removal.

January 2023

DECEMBER 2022

Work continues on both the interior and exterior of the building. First passenger elevator has been commissioned and is operational.

December 2022

NOVEMBER 2022

Work continues on both the interior and exterior of the building. Main Entrance Lobby is tiled and drywalled.

November 2022

OCTOBER 2022

Work continues on both the interior and exterior of the building. Green roofs being installed.

October 2022

SEPTEMBER 2022 UPDATE

Work continues on both the interior and exterior of the building. Landscaping of the front courtyard continues.

September 2022

AUGUST 2022 UPDATE

Work continues on both the interior and exterior of the building. Landscaping of the front courtyard has begun.

July 2022

June 2022 Update

Overhead protection was dismantled. Interior work restarting now that labour strikes have finished.

June 2022

May 2022 Update

Brick work was finished on the north elevation, completing the exterior masonry. Last remaining precast panels were installed and alignment continues. Interior work continues, but with several key trades on strike - drywallers, tile, carpet and hardwood installers - progress has slowed considerably. Hopefully the strikes will end soon and production can ramp back up.

wellesley-may-2022-update-3
wellesley-may-2022-update-3
wellesley-may-2022-update-3
May 2022

April 2022 Update

Masonry on the north elevation continues. Interior work continues.

202205-wellesley-brick-update
202205-wellesley-corridor-update
April 2022

March 2022 Update

Major milestones Tower Crane was dismantled and removed from the building. Pre-cast panels have all been installed.

202204-wellesley-tower-crane
202204-wellesley-tower-crane
March 2022

February 2022 Update

Balcony railings frame and glass continues being installed. Plumbing and electrical wiring continues throughout the building.

20220301-wellesley-electrical-wiring
February 2022

January 2022 Update

Precast continues to be placed. Passenger elevators are being installed. Drywalling of suites continues.

20220202-wellesley-jan-update-elevator
20220202-wellesley-jan-update-dry-wall
January 2022

December 2021 Update

Concrete structure is now substantially complete. Views from the top!

20220104-wellesley-view-from-the-top
November 2021

November 2021 Update

The final floor slab has now been poured with only one set of walls and the roof to complete. Work continues on both the exterior and interior of the building.

202111-wellesley-exterior-update
October 2021

October 2021 Update

We are approaching the top of the building with the 28th floor walls being worked on. At the same time, drywall installation has started on the lower floors.

202110-wellesley-update
September 2021

September 2021 Update

Brick work completed on east elevation. During September our forming contractor experienced a COVID outbreak amongst their crew. As a result, they were unable to work for the better part of two weeks. While no other trades were impacted directly, work was slowed substantially, especially while the crane operator was not on site.

202109-wellesley-brick-work
202109-wellesley-update-1
202109-wellesley-update
August 2021

August 2021 Update

Brick work continues on east elevation. Windows and exterior doors continue to be installed as do interior steel studs.

202108-wellesley-update-brick-work-east
202108-wellesley-window-interior
August 2021

July 2021 Update

Brick work beginning on east elevation. Windows and precast continue being installed.

202107-wellesley-east-elevation
202107-wellesley-brick-work-update
July 2021

June 2021 Update

Brick work complete on west elevation. Both car elevators now complete.

20210706-wellesley-north-side
June 2021

May 2021 Update

Brick work is now underway. Precast panels continue to be installed.

20210601-wellesley-precast
20210601-wellesley-june-update-Brick
May 2021

April 2021 Update

Windows are being installed. The scaffold system installed so that the masonry can begin.

20210504-wellesley-november-update-Masonry-Scaffold
20210504-wellesley-Installed Windows
20210504-wellesley-exterior-fasade-windows
April 2021

March 2021 Update

The Tower Crane has been raised again. Work continues above ground, below ground, and on the interior and exterior walls.

20210504-wellesley-Installed Windows
20210504-wellesley-exterior-fasade-windows
20210504-wellesley-november-update-Masonry-Scaffold
March 2021

February 2021 Update

In spite of a few days lost to -20 degree temperatures and snow, construction continues. Precast concrete is being hung, interior block walls are being placed, and installation of steel studs has commenced as well. The first car elevator is operational.

202102-View-of-Steel-Studs-front-building-perspective-3
202102-First-Car-Elevator-operational-4
202102-Precast-Concrete-at-Ground-Level-scaled-2
February 2021

January 2021 Update

Construction continues while all health and safety protocols, including those for COVID, continue to be followed. Installation of precast panels continues; west side of ground floor nears completion.

20201224-South perspective from Maitland St
20201224_chuck-st-west-perspective
January 2021

December 2020 Update

Construction continues while all health and safety protocols, including those for COVID, continue to be followed.

November 2020

November 2020 Update

Above Ground: Double manhoists on site being finalized for use. Amenity area forming complete. Below Ground: First car elevator being finalized for use. Installation of block walls continues.

202010-Above-Ground- Double-Hoist-Platform
202010-Below-Ground-Block-Work
October 2020

October 2020 Update

Toronto Hydro finally completed energizing the building. Generator and Power Shack have now been removed. Hoist scheduled to be installed shortly.

20201031-Generator-Removed
September 2020

September 2020 Update

As we continue to build upwards, the tower crane has been raised once, and will be raised again shortly, to keep pace with construction. We are still waiting on Toronto Hydro to make their final connection to the building.

202010-Top-of-building
202009-Underground-Parking
August 2020

August 2020 Update

Public Art has been installed on the overhead protection. Prepared by Toronto artist Andrew Owen, the art celebrates the diversity of the Church and Wellesley area. Work continues below grade - with car elevators being installed and the Hydro vault ready for connecting. Above ground slabs and walls continue to be poured.

202008-Overhead-Graphics-with-Painted-Plywood
202008-Car-Elevator-being-installed
202008-Graphics and Building Front
July 2020

July 2020 Update

While continued hot weather slowed down production somewhat, good progress continues to be made above and below grade.

June 2020

June 2020 Update

Overhead protection has been installed. Keep an eye out for the public art - coming soon!

May 2020

May 2020 Update

Construction continues to progress as restrictions across the province are slowly being lifted. Above and below grade work continues to progress while maintaining all COVID protocols.

Next Arrow
Toronto Studio, 1 - 3 bedroom condos, Eighty One Wellsey by Aragon Properties, highrise, downtown toronto, the village toronto

AT HOME 

IN THE

VILLAGE

Toronto Studio, 1 - 3 bedroom condos, Eighty One Wellsey by Aragon Properties, highrise, downtown toronto, the village toronto

Rising 28 storeys above the Church-Wellesley Village in downtown Toronto, 81 Wellesley is a sophisticated addition to a vibrant neighbourhood. Outdoor and retail spaces were designed to encourage interaction, inviting people to slow down and spend time with neighbors and friends. We carried the mid-century modern aesthetic of the exterior architecture into the interiors, which are stylish yet unpretentious.

HOME CONSTRUCTION REGULATORY CERTIFICATE